Preah Sihanouk: Preah Sihanouk provincial authorities said that as of the 17th In July 2020, the project decided to pour 99.92% concrete, install 100% drainage, prepare 59.99% granite, and pave the floor. Granite was 4.48%, light poles were installed on public roads 23.89%, and light bulbs were installed using intelligent technology 10.45% of Planted light poles.

On the morning of Friday, July 17, 2020, HE Kouch Chamroeun, Governor of Preah Sihanouk Province, accompanied HE Chea Sophara, Deputy Prime Minister and Minister of Land Management, Urban Planning and Planning. Construction and Chairman of the National Committee for Coastal Management and Development of Cambodia (CCHR) HE Thong Khon, Minister of Tourism and As the Permanent Vice President of the NCDD A. His Excellency Say Sam Al, Minister of Environment and Deputy Chairman of CEC, inspected the progress of the implementation of the Urban Road Infrastructure Project. 34 lines of 82,574 km in Sihanoukville.

The project is also preparing to rehabilitate the beach and build two wastewater treatment plants, the first near the Sunshine Bay Hotel. Filtration capacity of 5,200 cubic meters per day reached 20% and secondly near Sokha Hotel, filtration capacity of 7,200 cubic meters per day reached 10%.



In addition, the project will pave rubber mats, prepare traffic signs and lights, and install security cameras on the roads, as well as build parking lots and public bathrooms in Along the coast as well.
By: Kolap